Nuclear Power Generation
We are growing into a company with the highest technology competitiveness by enhancing business competitiveness and management innovation.
- Business Introduction
- Nuclear Power Generation
Business Information
As a qualified maintenance company of Korea Hydro & Nuclear Power Co., Ltd., with major business sites in nuclear power plants, we are fulfilling our responsible roles in all fields of nuclear power plant maintenance, including commissioning maintenance, routine maintenance, scheduled outage maintenance and modification & rehabilitation work, contributing to the prevention of power plant unexpected breakdowns, improvement of facility utilization rates and stable power supply.
Major Work
-
Commissioning and Maintenance
We participate in the commissioning phase (36 months before completion), the final stage of nuclear power plant construction, to support various tests of systems and equipment, and we ensure the reliability and soundness of the facility during future commercial operation by early identifying vulnerable facilities and equipment characteristics, and improvement of convenience facilities for maintenance.
-
Routine Maintenance
We prevent breakdowns in advance through periodic preventive maintenance and predictive diagnosis in the operating state of the power plant, and normalize the facility by performing prompt maintenance when a failure occurs.
-
Scheduled Outage Maintenance
Using the periodic inspection and refueling periods under the Nuclear Act and the Electricity Business Act (18-month cycle), various inspections that cannot be performed during normal operation of the plant, large-scale facility improvements, or maintenance replacement are performed.
-
Modification and Rehabilitation
We contribute to efficient maintenance of facilities through performance improvement work, life extension work, facility improvement and repair work, excluding routine maintenance and scheduled outage maintenance work.
Thermal Power Plant
-
Hanul Nuclear Power Plant
- Oder from Korea Hydro & Nuclear Power Co., Ltd.
- Location Uljin, Gyeongbuk
- Capacity #3,4 : 1000MW*2
- Project Content Primary and secondary power generation facilities, water intake facilities, routine maintenance and scheduled outage maintenance
- Fuel Source Nuclear Power
-
Hanbit Nuclear Plant
- Oder from Korea Hydro & Nuclear Power Co., Ltd.
- Location Younggwang, Jeonnam
- Capacity #1~6 : 5900MW
- Project Content Routine maintenance and operation of water treatment facilities
- Fuel Source Nuclear Power
-
Kori Nuclear Power Plant
- Oder from Korea Hydro & Nuclear Power Co., Ltd.
- Location Gijang, Busan
- Capacity #2~4, Shinkori #1~2 : 4550MW
- Project Content Routine maintenance and scheduled outage maintenance of water intake facilities
- Fuel Source Nuclear Power
-
Barakah Nuclear Power Plant
- Oder from Korea Hydro & Nuclear Power Co., Ltd.
- Location Barakah, UAE
- Capacity #1~4 : 1400MW*4
- Project Content Commissioning and Maintenance
- Fuel Source Nuclear Power
Performance
Plants | Oder from | Unit | Capacity (MW) |
Project Content |
Generation Method |
Project Date |
---|---|---|---|---|---|---|
Hanul Nuclear Power | Korea Hydro & Nuclear Power Co. | 3,4 | 1000*2 | Routine and Scheduled Outage Maintenance | Nuclear Power | 2017.04 ~ present |
Hanul Nuclear Power | Korea Hydro & Nuclear Power Co. | 1~6 | 950*2 / 1000*4 | Routine and Scheduled Outage Maintenance of water intake facilities | Nuclear Power | 2021.03 ~present |
Kori Nuclear Power | Korea Hydro & Nuclear Power Co. | 2~6 | 650*1 / 950*2 / 1000*2 | Routine and Scheduled Outage Maintenance of water intake facilities | Nuclear Power | 2021.02 ~ present |
Hanbit Nuclear Power | Korea Hydro & Nuclear Power Co. | 1~6 | 950*2 / 1000*4 | Operation and Routine maintenance of water treatment facilities | Nuclear Power | 2019.11 ~ present |
BNPP | KEPCO KPS | 1~4 | 1400*4 | Commissioning and maintenance of mechanical equipment | Nuclear Power | 2015.06 ~ present |
Saeul Nuclear Power | Korea Hydro & Nuclear Power Co. | 1,2 | 1400*2 | Operation and Routine maintenance of water treatment facilities | Nuclear Power | 2019.11 ~ 2022.02 |
Wolsong Nuclear Power | Korea Hydro & Nuclear Power Co. | 1~6 | 678*1 / 700*3 / 1000*2 | Operation and Routine maintenance of water treatment facilities | Nuclear Power | 2014.10 ~ 2019.10 |
Saeul Nuclear Power | KEPCO KPS | 1,2 | 1400*2 | Commissioning and maintenance of mechanical equipment | Nuclear Power | 2011.05 ~ 2019.08 |
Wolsong Nuclear Power | KEPCO KPS | 5,6 | 1000*2 | Commissioning and maintenance of mechanical equipment | Nuclear Power | 2010.01 ~ 2015.07 |
Kori Nuclear Power | KEPCO KPS | 5,6 | 1000*2 | Commissioning and maintenance of mechanical equipment | Nuclear Power | 2009.04 ~ 2012.07 |